horak Rechtsanwälte – Vergaberecht

Public procurement for contracting authorities and bidders

Cancellation of procurement and damages

An authority may need to stop a procurement, but cancellation requires a careful distinction between the relevant procedural ground and possible liability. Bidders should examine the actual reasons, available remedies and evidence of their own loss.

Assess the reason

Changes in need, financing problems, defects in the process or uneconomic results require different analysis. The applicable provision and actual facts must support the decision. A budget estimate that was unrealistic from the outset does not automatically make all submitted prices uneconomic. Record the assessment rather than relying on a formulaic cancellation notice.

Distinguish termination from liability

Even where an authority is not compelled to award a contract, ending the process can have legal consequences. The assessment of cancellation, the available procurement remedy and damages are not interchangeable. A bidder cannot assume that every unlawful cancellation gives it the contract or the entire expected profit.

Bidders should preserve their position

Secure the notice, reasons, submitted offer and relevant correspondence. Examine whether a similar procurement is being restarted and whether the stated change in need is genuine. Complaint and review deadlines may matter. For compensation, establish the relevant duty, causation, realistic award opportunity and actual loss.

Prepare a defensible decision

Authorities should compare alternatives, explain why correction or continuation is unsuitable and assess their own responsibility for the problem. Consider how bidders will be informed and how a later procurement will be structured. A new title for essentially the same requirement does not by itself explain an earlier cancellation.

Four practical examples

The following scenarios are illustrative, not reports of actual client matters. The outcome depends on the documents and circumstances of the individual procurement.

Example 1: Funding disappears

The intended finance is unavailable after bids arrive. Assess the procedural ground and responsibility for the situation. A real funding gap does not automatically eliminate every damages risk.

Example 2: Prices above estimate

All offers exceed the internal estimate. Check whether the estimate was current and realistic before concluding that the competition was uneconomic. The market evidence must be considered.

Example 3: Renamed project

The authority cancels and advertises nearly the same requirement again. Examine the real change and the stated reasons. A different project name is not a substantive justification.

Example 4: Lost profit claim

A bidder seeks its anticipated profit. It must establish more than a procedural error. The hypothetical lawful outcome, causation and loss require a detailed evidential assessment.

Related topics

Damages and other procurement claims · Review before the Vergabekammer · Public procurement advice for contracting authorities

Discuss your procurement

For a review, please identify the authority, contract or lot, current procedural stage and any deadline. We can then clarify the scope of the requested work. Contact our team. An enquiry does not itself create a retainer or preserve a legal deadline.

Legal sources

Official legislation and materials, some in German: § 63 VgV – Aufhebung · § 181 GWB – Vertrauensschaden · § 160 GWB – Nachprüfung · § 280 BGB – Schadensersatz

Updated 13 November 2026. Illustrative guidance on German and EU procurement law.